Building Walls
July 26th, 2008

This past saturday, we started building walls
Sunday was another wet & rainy day

We currently have 4 walls built
one interior and the others exterior
just not quite ready to erect.
Hot & Humid!!!
July 20, 2008
The subfloor is DONE!
We may have to do some patch work later because it was rained on
Trimming the edge of the subfloor
Getting ready to build another wall
85 degrees and alot of humidity - made for a miserable day of work
But we were able to get quite a bit done today, after losing saturday to rain!
Rainy and Wet!
July 19th, 2008
4 inches of rain during the week...
..& another full day of rain today...
we realized that no matter how much we try, our subfloor will still get wet.
Landscaping
July 16th, 2008

No more piles of dirt
Wow! I just realized...we have a huge yard.
We will need plenty of grass seed and plenty of volunteer lawn mowers.
Garage & Septic continued...
July 15th, 2008
Garage
Septic System
We hired someone to do the Septic system.
It was 91 degrees yesterday when they put our system in the ground.

Garage & Septic
July 14th, 2008

Sand for garage floor

And I thought we'd have to mow the garage one of these days : )


Digging trench for the septic system



Septic comes directly into the utility rm. in the basement
Sand for garage floor
And I thought we'd have to mow the garage one of these days : )
Digging trench for the septic system
Septic comes directly into the utility rm. in the basement
SubFloor
July 13th, 2008
A bit of adhesive
plywood and some nails...
that should do it!
Shade in the basement! With another week of 90 degree weather predicted...this will come in handy.
Isn't it Beautiful?!
July 12th, 2008
Working on the octagon cantilever for the Master Bedroom


Isn't it Beautiful?!
I Love it!
I Love it!
Ribbons & Strongbacks
July 6th, 2008
For the past 2 1/2days, we have been connecting the trusses to each other...
(these are called strongbacks) & we added Ribbons to the outside edge of each truss to connect them together.
(these are called strongbacks) & we added Ribbons to the outside edge of each truss to connect them together.
Including a cute lil' wall that I made for between the stairs and the garage.
The 2nd delivery of lumber allowed us to be able to work on the cantilevered area for the Master Bdrm.