October 3rd-5th On Friday, we started putting up Fascia boards. Holes were dug for five load bearing columns needed for front entrance & garage. Each hole was dug to 4 feet, then cardboard tubes inserted. Concrete was mixed and poured into each tube. The basement window well on the northside was installed, followed by pea rock & black dirt.
Eventually more dirt will need to be backfilled, level with the window well.
We couldn't have done all this without help. Thanks guys!!